Keighley, West Yorkshire · Leeds Magistrates Court
A scaffolder installing temporary edge protection at a site in Keighley stepped on a roof skylight while carrying materials and fell more than 6 metres to the warehouse floor below. STM360 Limited was the principal contractor found in breach of construction regulations over the fragile-surface risk; a second firm, Clover Access Systems Limited, was fined separately in the same case.
Injuries: Broken arm, broken leg and head lacerations.
Construction (Design and Management) Regulations 2015, Regulation 13
“His fall was wholly avoidable; the risks associated with work on, or around fragile surfaces are well-known.”
Fragile roof surfaces such as skylights must be identified and protected before anyone works on or near a roof, regardless of the specific task being carried out.